Houlton Border Crossing Paving
Work included milling and paving of over 97,000 square feet of an active border crossing. Areas that were paved included booth areas, vehicle inspection areas, commercial truck inspection areas and two GSA parking lots. All parking lots and designated lanes were striped after hours to help prevent disruption of the flow of traffic.
Project Details
- Provided loaming & seeding around parking area
- Replaced curb stops
- Loamed & seeded between northbound and southbound lanes
- Milled existing paving
- Shimming
- Repaved two parking lots estimated at 97,000 sq.ft.
Company: Lander Group, LLC
Owner: General Services Administration
Year: 2012
Location: Border Crossing LPOE, Houlton, Maine